Wallonia ordered Google to suspend construction on a building at its planned Farciennes data centre, saying it was built without proper planning permission. Google says it has paused work and will comply with local laws; its court challenge to a separate refusal over water cooling is due for a hearing in January.
Wallonia’s regional authorities have ordered Google to stop construction on a building at its planned Farciennes data centre, saying the three-hectare structure was built without proper planning permission. Google says it has paused work while awaiting further guidance, leaving the project’s timetable uncertain as the company challenges a separate regional decision over its proposed use of river water for cooling.
Regional inspectors visited the site on Thursday and told Google representatives to halt construction, the authority said. Nicolas Yernaux, a spokesperson for the Wallonia regional government, described the structure as a “major offense” and said it covered three hectares. AFP reported the order on Friday. The order itself was not available online in the source reporting, so its full terms and any conditions for resuming work have not been independently established here.
Google told the BBC it had paused the works “pending additional guidance.” The company also said it had operated in Belgium for more than 15 years and remained “committed to complying with local laws.” Those statements confirm Google’s position; they do not resolve the regional authority’s allegation about the building’s permission.
The dispute also involves the site’s cooling plans. The project was initially designed to use air cooling, according to Belgian media cited by AFP. Google later sought permission to change the plan and draw water from the nearby River Sambre. Wallonia refused that application over the summer, with concerns about water use sharpened by severe droughts since spring, AFP reported. Google has challenged the refusal in court, with a hearing scheduled for January.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Permit Dispute Puts Site Timetable at Risk
The stop-work order affects a specific building, not necessarily every part of the planned data centre. But construction cannot proceed on the affected work while the order remains in force, and the reporting does not establish when or under what conditions it might restart. That creates uncertainty for Google and for contractors or suppliers tied to the project.
The case also shows how planning permission and water access can affect the timing of infrastructure intended to support cloud computing and AI services. Data centres need substantial electricity and cooling, and local approval processes can shape where capacity is built and when it becomes available. The source reporting does not quantify the proposed water use or estimate any effect on Google’s service capacity, so the consequences for customers remain unknown.
For residents, the dispute puts local decisions about land and river water at the centre of a major technology project. Greenpeace Belgium has criticized the construction, but its allegations are not a court finding. The regional authority’s order is the confirmed regulatory action; the underlying legal dispute has not been settled.
Products Worth Considering

Ledger Nano X Crypto Hardware Wallet – Bluetooth (Black + Billfodl)

Logitech MX Creative Console with 9 Customizable Keys, Graphite

LG UltraGear 27G640A-B 27-Inch QHD IPS Gaming Monitor, 300Hz, 1ms, G-SYNC Compatible, FreeSync Premium, DisplayHDR 400, HDMI 2.1, USB-C, Adj
As an affiliate, we earn on qualifying purchases.
How the Cooling Plan Became a Dispute
The Farciennes project is being built on a former mining site covering about 50 hectares, according to AFP. The structure cited by Wallonia accounts for three hectares of that area. AFP’s reporting says the original design used air cooling, before Google applied to change the plan to use water from the Sambre. The regional government rejected that change during the summer.
Greenpeace Belgium said in a report this week that drone footage showed construction continuing and that the latest version of the planning permission had been revoked in August. The group said Google was continuing work despite the permit issue. These are claims made by an environmental organization, not findings established by a court. The regional authority subsequently ordered construction to stop, according to statements reported by AFP.
The Farciennes dispute is not the only reported challenge facing Google’s data centre construction. AFP reported that Finnish authorities halted work at two Google data centre sites in October. The source material provides no further details about those cases, and they should not be treated as evidence about the legal status of the Belgian project.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
Legal Status and Water Use Remain Open
The available reporting does not include the written stop-work order, the full planning record, or a final legal ruling on whether the building was constructed without the required permission. It is also unclear whether the structure can be brought into compliance, whether the order covers any work beyond the building identified by the regional authority, or what steps Google would need to take before construction could resume.
The water-cooling application is a separate issue from the authority’s stated reason for the stop-work order. Google has challenged the refusal in court, but the reporting does not specify the amount of water the proposed system would use, the precise environmental conditions behind the decision, or whether Google could revise its application. Greenpeace’s account of continued construction and the revoked permit is a campaign group’s claim; it has not been established through a reported court decision.
January Hearing and Possible Site Guidance
The next reported milestone is the January court hearing on Google’s challenge to Wallonia’s refusal of the water-cooling application. The source material does not provide an exact hearing date or say when a decision is expected. Separately, Google says it is waiting for additional guidance on the paused works.
Until the regional authority clarifies the order or the relevant legal proceedings produce a decision, the status and schedule for the affected construction remain uncertain. No date for resuming work, revised building plan, or resolution of the planning-permission dispute has been reported.
Key Questions
Why did Wallonia order construction to stop?
The regional authority said a three-hectare building at the Farciennes site was being built without proper planning permission. A spokesperson called it a major offense, according to AFP.
Has Google stopped work at the site?
Google told the BBC it had paused the works pending additional guidance. The reported order concerns the building identified by the authority; the available information does not establish that every activity across the wider site has stopped.
What is the dispute over the River Sambre?
Google applied to change the project’s cooling plan from air cooling to a system using water from the River Sambre. Wallonia refused the application over the summer. Google has challenged that refusal in court, with a hearing scheduled for January.
Has a court ruled that Google broke the law?
The source reporting describes a regional order and an unresolved legal dispute, not a final court finding. The authority’s allegation about planning permission should not be treated as a court ruling.
When could construction resume?
No restart date has been reported. Google says work is paused while it awaits guidance, and the source material does not say what conditions would have to be met before the affected construction could resume.